Vista Construction Updates

  • Pipe Installation on South Melrose Drive

    May 9, 2014

    Construction crews have reached the intersection of Lionshead Avenue and South Melrose Drive. Construction work will begin the week of May 12. Read more.

  • Crews to Install Pipeline on South Melrose Drive in April

    Updated April 4, 2014

    March 25, 2014

    Construction crews are moving their way west along Lionshead Avenue and are quickly approaching the South Melrose Drive intersection. The Eagle Drive intersection is now open.   In mid-April, crews will close access to Lionshead Avenue from South Melrose Drive for approximately six weeks to trench through the intersection. Read more.

  • Crews to Wrap-up Work Prior to Street Restorations

    March 14, 2014

    You may have noticed that the Carlsbad Desalination Project crews have returned to the cities of Vista and San Marcos. Over the next three weeks, crews are working to complete pipeline installation activities in select areas along Poinsettia Avenue and W. Linda Vista Drive prior to beginning final street restorations in April. Read more.