March 14, 2014
You may have noticed that the Carlsbad Desalination Project
crews have returned to the cities of Vista and San Marcos. Over the next three
weeks, crews are working to complete pipeline installation activities in select
areas along Poinsettia Avenue and W. Linda Vista Drive prior to beginning final
street restorations in April. Crews will also begin conducting pipe inspections
and monitoring on Las Flores Drive the week of March 24. All work is scheduled
to be complete in April.
Construction hours are scheduled from 7:00 a.m. to 5:30 p.m.
During construction, drivers should expect temporary lane closures, detours,
reduced land widths and equipment along the route and should use caution and
allow more time to reach their destinations.
Posted on Fri, March 14, 2014
by T. Whipple